In April 2016 LOC Foundation, with the help of Victory Christian Center from, Texas, started the construction of the new office building and therapy center. After an epic eight days of hard work, the 5812.51 square feet building was standing up and it had a roof on.
The construction is 100% funded through donations. Stichting Livada from Netherlands and a private donor gave later that year towards the exterior and interior of the building.
The progress continued in September 2016 when we managed to put up the new roof of the building. Then in November we were able to put in the new windows and external doors and this way the building was safe throughout the hard winter.
In March 2017 we started working in the interior with electrical installations (including cables for internet, security alarm and external cameras), the pipes for the central heating system that go inside the walls, internal insulation and also we were able to put up the drywall for the first floor.
On April the 3rd we started working on the external insulation. We are very grateful for the construction team from Victory Christian Center and all the donors that helped financially to get so far with the construction. As we still have more work to do on the construction we pray and challenge more donors to help us continue and finish the construction as we still need a new heating system, floors, interior doors, etc. May the Lord richly bless every single person who blessed us throughout this process. THANK YOU!